*This report is submitted from ICS on a weekly basis.
Centennial Elementary
Completed week ending Friday, May 8, 2020:
- Completed packing and moving efforts throughout the building.
- Completed an on-site coordination meeting with District Food Services and Trimark (Kitchen Eq. contractor).
- Completed plumbing fixture demolition in all of Area A.
- Abatement contractor continued flooring and chalkboard removal.
- Completed hanging and taping of drywall in the former Media Center area.
- Completed MEP rough-in in the former Media Center area.
- Completed mechanical insulation in the former Media Center area.
Planned week ending Friday, May 15, 2020:
- Continue electrical rough-in at the new transformer location.
- Begin painting in the former Media Center area.
- Abatement contractor to complete remaining abatement scope.
- Continue plumbing fixture demolition in Area B.
- Continue MEP demo in Area A.
- Begin MEP rough-in in Area A.
Middle School
Completed week ending Friday, May 8, 2020:
- Moved third floor existing classroom furniture into storage trailers.
- Finished abatement on third floor.
- Started abatement on main level.
- Finished mechanical and electrical rough-ins in the Media Center.
- Finished drywall in the Media Center.
- Started putting floor protection down in corridors.
Planned week ending Friday, May 15, 2020:
- Finish abatement on main level.
- Start demolition on third level.
- Install locker protection.
- Move existing furniture out of second and main level.
Sheridan Hills Elementary
Completed week ending Friday, May 8, 2020:
- District staff continued packing efforts in anticipation of the renovation.
- District IT began removing technology items from rooms in anticipation of the renovation.
- Material submittals continue to be submitted and reviewed.
- Corval Constructors installed temporary fencing around the staging areas.
Planned week ending Friday, May 15, 2020:
- Abatement contractor to begin flooring, chalkboard and pipe insulation removal in Area C.
- District IT to continue removal of technology items.
- Corval Constructors to continue mobilization efforts and begin installing temporary protection throughout the building.
Richfield High School
Completed week ending Friday, May 8, 2020:
- Area C (new IT tech space/health classroom/flex)
- Finish low voltage and punch list items
- Area C (third floor conference room)
- Completed mechanical and electrical finishes
- Finish wall tile and punch list
- Old courtyard (expanded commons)
- Finished polishing of terrazzo flooring
- Front Entrance Stair Tower
- Punch list and final clean
- Area P
- Continued above grade masonry wall installation
- Started underground sewer work
- Area D and E Bathrooms
- Mechanical and electrical rough-ins for Area D
- Sheetrocked walls in Area D
- Old Concession Stand
- Completed room finishes and punch list
- Old Board Room
- Finished mechanical and electrical rough-ins
- Started drywall work
- Lower Level Area F (Old locker rooms, new weight room)
- Started demolition
- Area G/H 1st and 2nd Level (Classrooms)
- Demolition
Planned week ending Friday, May 15, 2020:
- Area P Link
- Continue exterior masonry walls
- Finish sewer work
- Area D and E Bathrooms
- Mechanical and electrical rough-ins for Area D
- Sheetrocking walls in Area D
- Old Concession Stand
- Ceiling work and final clean
- Old Board Room
- Finish drywall work
- Start painting
- Lower Level Area F (Old locker rooms, new weight room)
- Continue demolition
- Area G/H 1st and 2nd Level (Classrooms)
- Start wall framing
- Mechanical and electrical rough-ins
R-STEM Elementary
Completed week ending Friday, May 8, 2020:
- Old Admin area (New Classrooms)
- Continued glazed block wall installation and patching
- Started demolition in the main level music suites
Planned week ending Friday, May 15, 2020:
- Continue demolition of music suite and kindergarten classrooms
- Abatement in boiler room
Dual Language
Completed week ending Friday, May 8, 2020:
- Punch list items continue to be addressed.
- Resumed testing and balancing efforts of the mechanical & HVAC system.
- ICS Commissioning continued commissioning efforts.
Planned week ending Friday, May 15, 2020:
- Continue to address punch list items.
- Continue testing and balancing of the mechanical/HVAC system.
- ICS Commissioning to continue commissioning efforts.