Main Navigation - Mobile

ICS Weekly Report: May 8, 2020

ICS Weekly Report: May 8, 2020

*This report is submitted from ICS on a weekly basis.

Centennial Elementary

Completed week ending Friday, May 8, 2020:

  • Completed packing and moving efforts throughout the building.
  • Completed an on-site coordination meeting with District Food Services and Trimark (Kitchen Eq. contractor).
  • Completed plumbing fixture demolition in all of Area A.
  • Abatement contractor continued flooring and chalkboard removal.
  • Completed hanging and taping of drywall in the former Media Center area.
  • Completed MEP rough-in in the former Media Center area.
  • Completed mechanical insulation in the former Media Center area.

Planned week ending Friday, May 15, 2020:

  • Continue electrical rough-in at the new transformer location.
  • Begin painting in the former Media Center area.
  • Abatement contractor to complete remaining abatement scope.
  • Continue plumbing fixture demolition in Area B.
  • Continue MEP demo in Area A.
  • Begin MEP rough-in in Area A.

Middle School

Completed week ending Friday, May 8, 2020:

  • Moved third floor existing classroom furniture into storage trailers.
  • Finished abatement on third floor.
  • Started abatement on main level.
  • Finished mechanical and electrical rough-ins in the Media Center.
  • Finished drywall in the Media Center.
  • Started putting floor protection down in corridors.

Planned week ending Friday, May 15, 2020:

  • Finish abatement on main level.
  • Start demolition on third level.
  • Install locker protection.
  • Move existing furniture out of second and main level.

Sheridan Hills Elementary

Completed week ending Friday, May 8, 2020:

  • District staff continued packing efforts in anticipation of the renovation.
  • District IT began removing technology items from rooms in anticipation of the renovation.
  • Material submittals continue to be submitted and reviewed.
  • Corval Constructors installed temporary fencing around the staging areas.

Planned week ending Friday, May 15, 2020:

  • Abatement contractor to begin flooring, chalkboard and pipe insulation removal in Area C.
  • District IT to continue removal of technology items.
  • Corval Constructors to continue mobilization efforts and begin installing temporary protection throughout the building.

Richfield High School

Completed week ending Friday, May 8, 2020:

  • Area C (new IT tech space/health classroom/flex)
    • Finish low voltage and punch list items
  • Area C (third floor conference room)
    • Completed mechanical and electrical finishes
    • Finish wall tile and punch list
  • Old courtyard (expanded commons)
    • Finished polishing of terrazzo flooring
  • Front Entrance Stair Tower
    • Punch list and final clean
  • Area P
    • Continued above grade masonry wall installation
    • Started underground sewer work
  • Area D and E Bathrooms
    • Mechanical and electrical rough-ins for Area D 
    • Sheetrocked walls in Area D
  • Old Concession Stand
    • Completed room finishes and punch list
  • Old Board Room
    • Finished mechanical and electrical rough-ins
    • Started drywall work
  • Lower Level Area F (Old locker rooms, new weight room)
    • Started demolition
  • Area G/H 1st and 2nd Level (Classrooms)
    • Demolition

Planned week ending Friday, May 15, 2020:

  • Area P Link
    • Continue exterior masonry walls
    • Finish sewer work
  • Area D and E Bathrooms
    • Mechanical and electrical rough-ins for Area D
    • Sheetrocking walls in Area D
  • Old Concession Stand
    • Ceiling work and final clean
  • Old Board Room
    • Finish drywall work
    • Start painting
  • Lower Level Area F (Old locker rooms, new weight room)
    • Continue demolition
  • Area G/H 1st and 2nd Level (Classrooms)
    • Start wall framing
    • Mechanical and electrical rough-ins

R-STEM Elementary

Completed week ending Friday, May 8, 2020:

  • Old Admin area (New Classrooms)
    • Continued glazed block wall installation and patching 
    • Started demolition in the main level music suites

Planned week ending Friday, May 15, 2020:

  • Continue demolition of music suite and kindergarten classrooms
  • Abatement in boiler room

Dual Language

Completed week ending Friday, May 8, 2020:

  • Punch list items continue to be addressed.
  • Resumed testing and balancing efforts of the mechanical & HVAC system.
  • ICS Commissioning continued commissioning efforts.

Planned week ending Friday, May 15, 2020:

  • Continue to address punch list items.
  • Continue testing and balancing of the mechanical/HVAC system.
  • ICS Commissioning to continue commissioning efforts.
First page of the PDF file: ICS_Weekly_Project_Update05-08-20

Read More

A teacher at Centennial is interviewed for the evening news.

Landing Nav