*This report is submitted from ICS on a weekly basis.
Centennial Elementary
Completed week ending Friday, May 29, 2020:
- Continued wall finishes in the Special Ed. Suite.
- Began plumbing, mechanical and electrical rough-in in the Media Center.
- Continued saw-cutting and removal of concrete slabs for underground plumbing and electrical throughout Areas A & B.
- Continued hydronic piping throughout Area A.
- Continued misc. metal stud partitions in Area A.
Planned week ending Friday, June 5, 2020:
- Begin ceiling grid in the Special Ed. Suite.
- Begin plumbing fixture installation in the Special Ed. Suite.
- Begin metal stud framing in the Media Center.
- Begin masonry block patching and tooting throughout.
- Continue saw-cutting and removal of concrete slabs in Areas A & B.
- Continue hydronic piping and pipe insulation in Areas A & B.
Middle School
Completed week ending Friday, May 29, 2020:
- Continued demolition of ceilings and ductwork on the 2nd and 3rd level classrooms and corridors.
- Removed flooring and walls in the main level classrooms for the new art and health classrooms.
- Framed walls and soffits for the new media center, break out spaces, production room, media stacks, and media commons.
- Abatement on 3rd level art classrooms.
- Demolition on main level for new staff restrooms.
Planned week ending Friday, June 5, 2020:
- Finish demolition on 2nd and 3rd level.
- Start demolition of ceilings in the Special Education Wing next to Cafeteria.
- Mechanical and electrical rough-in work in the Media Center.
- Drywall work in the new Media Center Frame back walls on 3rd level for resource areas.
Sheridan Hills Elementary
Completed week ending Friday, May 29, 2020:
- Continued architectural demo in the bathrooms.
- Began demolition of soffits in Areas A & B.
- Began architectural, mechanical and electrical demo in the main level of Area C.
- Began mechanical, electrical rough in in the future Admin Suite and areas not under containment on Level 2 in C wing.
- Abatement contractor completed flooring removal in the Gym and Level 1 C wing.
- Began abatement efforts on Level 2 in C wing.
Planned week ending Friday, June 5, 2020:
- Continue abatement efforts on Level 2 in C wing.
- Continue mechanical, electrical rough in in the future Admin Suite.
- Continue ceiling demolition, as required, in classrooms and corridors.
- Continue architectural demo in the restrooms and throughout Areas A & B.
- Continue mechanical and electrical demo throughout Areas A & B.
Richfield High School
Completed week ending Friday, May 29, 2020:
- Boiler Room
- Finished setting all boilers
- Started connecting boilers
- Area P Link
- Continued east exterior masonry wall
- Area D and E Bathrooms
- Wall and floor tile
- Old Concession Stand
- Painting, ceiling and flooring
- Old Board Room
- Finished painting
- Flooring
- Lower Level Area F (Old locker rooms, new weight room)
- Finished demolition
- Mechanical and electrical rough-in in ceiling and in concrete floors
- Infilled concrete floors
- Started masonry walls
- 2nd and 3rd level science rooms
- Ceilings, mechanical and electrical rough-ins
- Wall and soffit framing
- Old Special Ed./New Athletics Commons
- Wall framing and mechanical/electrical rough-ins
- New Athletic Corridor/Elevator
- Excavation for new elevator
- Drywall work in new bathrooms
Planned week ending Friday, June 5, 2020:
- Boiler Room
- Continue mechanical and electrical connections of the boilers
- Area P Link
- Finish exterior wall and start steel structures
- Area D and E Bathrooms
- Finish tile work
- Start installing plumbing fixtures and painting
- Old Concession Stand
- Continue flooring
- Old Board Room
- Punch list and final clean
- Lower Level Area F (Old locker rooms, new weight room)
- Mechanical and electrical rough-ins
- Build interior masonry walls
- Wall sawing
- 2nd and 3rd level science rooms
- Mechanical and electrical rough-ins
- Old Special Ed./New Athletics Commons
- Drywall work
- Painting and ceiling installation
- New Athletic Corridor/Elevator
- Footings and masonry walls for elevator and storage room
R-STEM Elementary
Completed week ending Friday, May 29, 2020:
- Abatement in the boiler room and tunnel areas.
- Infilled the tiered concrete floor in the band room.
- Set door frames in the music suite and special education suite.
- Built masonry walls for the calm rooms in the special education suite.
- Electrical and drywall work in the pre-kindergarten rooms.
- Hydronic piping in the kindergarten classrooms.
Planned week ending Friday, June 5, 2020:
- Continue abatement in the boiler room and tunnel areas.
- Hang HVAC ductwork in the classrooms and music/special education suite.
- Frame walls in the music/special education suite.
- Drywall work in the pre-kindergarten classroom.
- Continue hydronic piping in classrooms.
Dual Language
Completed week ending Friday, May 29, 2020:
- Punch list items continue to be addressed.
- Continued to address mechanical/HVAC test and balance deficiencies.
- Contractors worked to address action items on the Commissioning Corrective Action Log.
Planned week ending Friday, June 5, 2020:
- Continue to address punch list items.
- Continue testing and balancing of the mechanical/HVAC system.
- ICS commissioning continued commissioning of the mechanical and HVAC systems.