ICS Weekly Report: May 29, 2020

ICS Weekly Report: May 29, 2020

*This report is submitted from ICS on a weekly basis.

Centennial Elementary

Completed week ending Friday, May 29, 2020:

  • Continued wall finishes in the Special Ed. Suite.
  • Began plumbing, mechanical and electrical rough-in in the Media Center.
  • Continued saw-cutting and removal of concrete slabs for underground plumbing and electrical throughout Areas A & B.
  • Continued hydronic piping throughout Area A.
  • Continued misc. metal stud partitions in Area A.

Planned week ending Friday, June 5, 2020:

  • Begin ceiling grid in the Special Ed. Suite.
  • Begin plumbing fixture installation in the Special Ed. Suite.
  • Begin metal stud framing in the Media Center.
  • Begin masonry block patching and tooting throughout.
  • Continue saw-cutting and removal of concrete slabs in Areas A & B.
  • Continue hydronic piping and pipe insulation in Areas A & B.

Middle School

Completed week ending Friday, May 29, 2020:

  • Continued demolition of ceilings and ductwork on the 2nd and 3rd level classrooms and corridors.
  • Removed flooring and walls in the main level classrooms for the new art and health classrooms.
  • Framed walls and soffits for the new media center, break out spaces, production room, media stacks, and media commons.
  • Abatement on 3rd level art classrooms.
  • Demolition on main level for new staff restrooms.

Planned week ending Friday, June 5, 2020:

  • Finish demolition on 2nd and 3rd level.
  • Start demolition of ceilings in the Special Education Wing next to Cafeteria.
  • Mechanical and electrical rough-in work in the Media Center.
  • Drywall work in the new Media Center Frame back walls on 3rd level for resource areas.

Sheridan Hills Elementary

Completed week ending Friday, May 29, 2020:

  • Continued architectural demo in the bathrooms.
  • Began demolition of soffits in Areas A & B.
  • Began architectural, mechanical and electrical demo in the main level of Area C.
  • Began mechanical, electrical rough in in the future Admin Suite and areas not under containment on Level 2 in C wing.
  • Abatement contractor completed flooring removal in the Gym and Level 1 C wing.
  • Began abatement efforts on Level 2 in C wing.

Planned week ending Friday, June 5, 2020:

  • Continue abatement efforts on Level 2 in C wing.
  • Continue mechanical, electrical rough in in the future Admin Suite.
  • Continue ceiling demolition, as required, in classrooms and corridors.
  • Continue architectural demo in the restrooms and throughout Areas A & B.
  • Continue mechanical and electrical demo throughout Areas A & B.

Richfield High School

Completed week ending Friday, May 29, 2020:

  • Boiler Room
    • Finished setting all boilers
    • Started connecting boilers
  • Area P Link
    • Continued east exterior masonry wall
  • Area D and E Bathrooms
    • Wall and floor tile
  • Old Concession Stand
    • Painting, ceiling and flooring
  • Old Board Room
    • Finished painting
    • Flooring
  • Lower Level Area F (Old locker rooms, new weight room) 
    • Finished demolition
    • Mechanical and electrical rough-in in ceiling and in concrete floors
    • Infilled concrete floors
    • Started masonry walls
  • 2nd and 3rd level science rooms
    • Ceilings, mechanical and electrical rough-ins
    • Wall and soffit framing
  • Old Special Ed./New Athletics Commons
    • Wall framing and mechanical/electrical rough-ins
  • New Athletic Corridor/Elevator
    • Excavation for new elevator
    • Drywall work in new bathrooms

Planned week ending Friday, June 5, 2020:

  • Boiler Room
    • Continue mechanical and electrical connections of the boilers
  • Area P Link
    • Finish exterior wall and start steel structures
  • Area D and E Bathrooms
    • Finish tile work
    • Start installing plumbing fixtures and painting
  • Old Concession Stand
    • Continue flooring
  • Old Board Room
    • Punch list and final clean
  • Lower Level Area F (Old locker rooms, new weight room)
    • Mechanical and electrical rough-ins
    • Build interior masonry walls
    • Wall sawing
  • 2nd and 3rd level science rooms
    • Mechanical and electrical rough-ins
  • Old Special Ed./New Athletics Commons
    • Drywall work
    • Painting and ceiling installation
  • New Athletic Corridor/Elevator 
    • Footings and masonry walls for elevator and storage room

R-STEM Elementary

Completed week ending Friday, May 29, 2020:

  • Abatement in the boiler room and tunnel areas.
  • Infilled the tiered concrete floor in the band room.
  • Set door frames in the music suite and special education suite.
  • Built masonry walls for the calm rooms in the special education suite.
  • Electrical and drywall work in the pre-kindergarten rooms.
  • Hydronic piping in the kindergarten classrooms.

Planned week ending Friday, June 5, 2020:

  • Continue abatement in the boiler room and tunnel areas.
  • Hang HVAC ductwork in the classrooms and music/special education suite.
  • Frame walls in the music/special education suite.
  • Drywall work in the pre-kindergarten classroom.
  • Continue hydronic piping in classrooms.

Dual Language

Completed week ending Friday, May 29, 2020:

  • Punch list items continue to be addressed.
  • Continued to address mechanical/HVAC test and balance deficiencies.
  • Contractors worked to address action items on the Commissioning Corrective Action Log.

Planned week ending Friday, June 5, 2020:

  • Continue to address punch list items.
  • Continue testing and balancing of the mechanical/HVAC system.
  • ICS commissioning continued commissioning of the mechanical and HVAC systems.