*This report is submitted from ICS on a weekly basis.
Centennial Elementary
Completed week ending Friday, May 22, 2020:
- Mechanical contractor demolished and removed an existing air handling unit out of the courtyard area.
- Abatement contractor continued flooring removal.
- Demolition was completed in the future Media Center Area.
- Concrete floor slab saw-cutting began in Area B.
- Architectural, Mechanical, Electrical and Plumbing demolition continued in Area B, mainly the existing Lounge and Nurse areas.
Planned week ending Friday, May 29, 2020:
- Abatement contractor to complete all remaining abatement scope.
- Begin underground plumbing rough-in in Area B.
- Continue painting in the former Media Center/future Special Education suite.
- Begin acoustical ceiling grid installation in the Special Education suite.
- Begin installation of lights, HVAC grilles/diffusers and plumbing fixtures in the Special Education suite.
Middle School
Completed week ending Friday, May 22, 2020:
- Demolition of ceilings on 3rd level classrooms and corridors.
- Demolition of ductwork on 2nd and 3rd level classrooms and corridors.
- Demolition of steam piping and unit ventilators on 2nd and 3rd level classrooms.
- Framed walls and soffits for new media center on 2nd level.
- Started mechanical and electrical rough-ins for new media center on 2nd level.
Planned week ending Friday, May 29, 2020:
- Demolition of walls and soffits on 3rd level.
- Continue demolition of ductwork on 2nd and 3rd level classrooms and corridors.
- Continue demolition of steam piping and unit ventilators on 2nd and 3rd level.
- Finish framing walls and soffits for new media center on 2nd level.
- Continue mechanical and electrical rough-ins for new media center on 2nd level.
Sheridan Hills Elementary
Completed week ending Friday, May 22, 2020:
- Abatement contractor continued removals in Level 1 of the C wing and Gym.
- Corval Constructors installed floor protection in the cafeteria and is now using this area as staging area.
- Corval Constructors continued demolition efforts in the Media Center.
- Corval Constructors began demolition in the A wing bathrooms, Nurse area and classrooms.
Planned week ending Friday, May 29, 2020:
- Abatement contractor to complete their removals in Level 1 of the C wing and begin setting up containments in Level 2 C wing.
- Corval Constructors to begin their demolition scope items in Level 1 of the C wing.
Richfield High School
Completed week ending Friday, May 22, 2020:
- Boiler Room
- Mechanical and electrical rough-ins and set boilers
- Area P Link
- Continued exterior masonry wall
- Area D and E Bathrooms
- Wall and floor tile
- Old Concession Stand
- Drywall work and taping of walls and soffits
- Started painting
- Old Board Room
- Installed ceilings
- Painting of walls
- Lower Level Area F (Old locker rooms, new weight room)
- Finish concrete floor slab removal
- Area C, G, and H 1st and 2nd Level (Classrooms)
- Demolition of ceilings, casework, and flooring
- Mechanical and electrical rough-in
- Wall framing
- New Athletic Corridor
- Below grade masonry
Planned week ending Friday, May 29, 2020:
- Boiler Room
- Finish setting boilers
- Mechanical and electrical connections to boilers
- Area P Link
- Finish exterior masonry wall
- Area D and E Bathrooms
- Tiling of walls and floors
- Old Concession Stand
- Finish painting
- Install flooring
- Old Board Room
- Mechanical and electrical finishes
- Start flooring
- Lower Level Area F (Old locker rooms, new weight room)
- Removal of mechanical and electrical piping
- Mechanical and electrical rough-ins
- Start infilling concrete floors
- Start masonry walls
- Area C, G, and H 1st and 2nd Level (Classrooms)
- Continue mechanical and electrical rough-ins
- Start framing walls and soffits in science rooms
- Drywall taping in classrooms
- New Athletic Corridor
- Underground waterproofing
- Dirt backfill of foundation walls
R-STEM Elementary
Completed week ending Friday, May 22, 2020:
- Finished abatement in music suite.
- Hydronic piping for corridor outside of music suite.
- Start framing kindergarten classrooms.
- Framing walls in pre-kindergarten classroom.
Planned week ending Friday, May 29, 2020:
- Infill floor in band room.
- Hang ductwork in music suite.
- Mechanical and electrical work in pre-kindergarten classroom.
- Tile branding wall.
Dual Language
Completed week ending Friday, May 22, 2020:
- Punch list items continue to be addressed.
- Continued to address mechanical/HVAC test and balance deficiencies.
- Contractors worked to address action items on the Commissioning Corrective Action Log.
Planned week ending Friday, May 29, 2020:
- Continue to address punch list items.
- Continue testing and balancing of the mechanical/HVAC system.
- ICS commissioning continued commissioning of the mechanical and HVAC systems.