Main Navigation - Mobile

ICS Weekly Report: May 22, 2020

ICS Weekly Report: May 22, 2020

*This report is submitted from ICS on a weekly basis.

Centennial Elementary

Completed week ending Friday, May 22, 2020:

  • Mechanical contractor demolished and removed an existing air handling unit out of the courtyard area.
  • Abatement contractor continued flooring removal.
  • Demolition was completed in the future Media Center Area.
  • Concrete floor slab saw-cutting began in Area B.
  • Architectural, Mechanical, Electrical and Plumbing demolition continued in Area B, mainly the existing Lounge and Nurse areas.

Planned week ending Friday, May 29, 2020:

  • Abatement contractor to complete all remaining abatement scope.
  • Begin underground plumbing rough-in in Area B.
  • Continue painting in the former Media Center/future Special Education suite.
  • Begin acoustical ceiling grid installation in the Special Education suite.
  • Begin installation of lights, HVAC grilles/diffusers and plumbing fixtures in the Special Education suite.

Middle School

Completed week ending Friday, May 22, 2020:

  • Demolition of ceilings on 3rd level classrooms and corridors.
  • Demolition of ductwork on 2nd and 3rd level classrooms and corridors.
  • Demolition of steam piping and unit ventilators on 2nd and 3rd level classrooms.
  • Framed walls and soffits for new media center on 2nd level.
  • Started mechanical and electrical rough-ins for new media center on 2nd level.

Planned week ending Friday, May 29, 2020:

  • Demolition of walls and soffits on 3rd level.
  • Continue demolition of ductwork on 2nd and 3rd level classrooms and corridors.
  • Continue demolition of steam piping and unit ventilators on 2nd and 3rd level.
  • Finish framing walls and soffits for new media center on 2nd level.
  • Continue mechanical and electrical rough-ins for new media center on 2nd level.

Sheridan Hills Elementary

Completed week ending Friday, May 22, 2020:

  • Abatement contractor continued removals in Level 1 of the C wing and Gym.
  • Corval Constructors installed floor protection in the cafeteria and is now using this area as staging area.
  • Corval Constructors continued demolition efforts in the Media Center.
  • Corval Constructors began demolition in the A wing bathrooms, Nurse area and classrooms.

Planned week ending Friday, May 29, 2020:

  • Abatement contractor to complete their removals in Level 1 of the C wing and begin setting up containments in Level 2 C wing.
  • Corval Constructors to begin their demolition scope items in Level 1 of the C wing.

Richfield High School

Completed week ending Friday, May 22, 2020:

  • Boiler Room
    • Mechanical and electrical rough-ins and set boilers
  • Area P Link
    • Continued exterior masonry wall
  • Area D and E Bathrooms
    • Wall and floor tile
  • Old Concession Stand
    • Drywall work and taping of walls and soffits
    • Started painting
  • Old Board Room
    • Installed ceilings
    • Painting of walls
  • Lower Level Area F (Old locker rooms, new weight room)
    • Finish concrete floor slab removal
  • Area C, G, and H 1st and 2nd Level (Classrooms)
    • Demolition of ceilings, casework, and flooring
    • Mechanical and electrical rough-in
    • Wall framing
  • New Athletic Corridor
    • Below grade masonry

Planned week ending Friday, May 29, 2020:

  • Boiler Room
    • Finish setting boilers
    • Mechanical and electrical connections to boilers
  • Area P Link
    • Finish exterior masonry wall
  • Area D and E Bathrooms
    • Tiling of walls and floors
  • Old Concession Stand
    • Finish painting
    • Install flooring
  • Old Board Room
    • Mechanical and electrical finishes
    • Start flooring
  • Lower Level Area F (Old locker rooms, new weight room)
    • Removal of mechanical and electrical piping
    • Mechanical and electrical rough-ins
    • Start infilling concrete floors
    • Start masonry walls
  • Area C, G, and H 1st and 2nd Level (Classrooms)
    • Continue mechanical and electrical rough-ins
    • Start framing walls and soffits in science rooms
    • Drywall taping in classrooms
  • New Athletic Corridor
    • Underground waterproofing
    • Dirt backfill of foundation walls

R-STEM Elementary

Completed week ending Friday, May 22, 2020:

  • Finished abatement in music suite.
  • Hydronic piping for corridor outside of music suite.
  • Start framing kindergarten classrooms.
  • Framing walls in pre-kindergarten classroom.

Planned week ending Friday, May 29, 2020:

  • Infill floor in band room.
  • Hang ductwork in music suite.
  • Mechanical and electrical work in pre-kindergarten classroom.
  • Tile branding wall.

Dual Language

Completed week ending Friday, May 22, 2020:

  • Punch list items continue to be addressed.
  • Continued to address mechanical/HVAC test and balance deficiencies.
  • Contractors worked to address action items on the Commissioning Corrective Action Log.

Planned week ending Friday, May 29, 2020:

  • Continue to address punch list items.
  • Continue testing and balancing of the mechanical/HVAC system.
  • ICS commissioning continued commissioning of the mechanical and HVAC systems.
First page of the PDF file: ICS_Weekly_Project_Update05-22-20

Read More

A teacher at Centennial is interviewed for the evening news.

Landing Nav