*This report is submitted from ICS on a weekly basis.
Centennial Elementary
Completed week ending Friday, June 5, 2020:
- Electrical connection cabinet placed on the exterior prefabricated pad.
- Electrical main switchboard cabinet installed.
- Wall finishes completed in the Special Ed. Suite.
- Began acoustical ceiling grid install in the Special Ed. Suite.
- Began concrete slab saw-cutting in the Boiler Room.
- Began painting in the classrooms and corridors.
- Completed metal stud framed walls in the Resource/Flex Classrooms (Area A).
Planned week ending Friday, June 12, 2020:
- Complete concrete slab saw-cutting in the Boiler Room.
- Continue above ceiling mechanical and electrical as well as underground electrical in the Media Center.
- Continue acoustical ceiling grid installation in the Special Ed. Suite.
- Continue mechanical and electrical rough-in in the Resource area.
- Continue wall finishes throughout the classrooms and corridors.
Middle School
Completed week ending Friday, June 5, 2020:
- Ductwork demolition on 2nd and 3rd floor.
- Demolition of walls and soffits on 3rd floor.
- Framing walls and soffits on 2nd floor stairwell entrances.
- Mechanical and electrical rough ins in 2nd floor classrooms.
- Wall framing and drywall work in Media Center.
Planned week ending Friday, June 12, 2020:
- Removal and demolition of classroom louvers.
- Continue framing walls and soffits on 2nd floor stairwell entrances.
- Continue mechanical and electrical rough-ins in 2nd floor classrooms.
- Wall framing and drywall work in Media Center.
- Start mechanical and electrical rough-ins on 3rd floor.
- Start framing walls and soffits on 3rd floor stairwell entrances.
Sheridan Hills Elementary
Completed week ending Friday, June 5, 2020:
- Completed Level 2 C wing demolition.
- Abatement contractor continued flooring and insulation removal in the Level 1 restrooms.
- Completed architectural demo in the Level 1 restrooms.
- Completed acoustical ceiling demolition in the Level 1 corridors.
- Continued above ceiling mechanical and electrical rough-in the Level 2 C wing.
- Begin masonry and hollow metal frame demo on Level 1.
Planned week ending Friday, June 12, 2020:
- Complete excavation for footings and foundations at the Front Entrance expansion.
- Begin footings and foundations at the Front Entrance expansion.
- Continue mechanical and electrical rough-in in Level 2 C wing.
- Continue mechanical and electrical rough-in in the future Front Admin Office.
- Demo acoustical ceilings in the existing Admin Office.
Richfield High School
Completed week ending Friday, June 5, 2020:
- Boiler Room
- Continued mechanical and electrical connections of the boilers
- Area P Link
- Finished exterior wall and removed scaffolding
- Area D and E Bathrooms
- Finished tile work
- Old Concession Stand
- Ductwork and ceiling work
- Old Board Room
- Punch list work and cleaning
- Lower Level Area F (Old locker rooms, new weight room)
- Mechanical and electrical rough-ins
- Build interior masonry walls
- Wall sawing Set door and frames
- 2nd and 3rd level science rooms
- Mechanical and electrical rough-ins
- Old Special Ed./New Athletics Commons
- Drywall work
- Painting and ceiling installation
- New Athletic Corridor/Elevator
- Footings and masonry walls for elevator and storage room
- Area A & B Art and Shop Classes
- Demolition
Planned week ending Friday, June 12, 2020:
- Boiler Room
- Continue mechanical and electrical connections of the boilers
- Area P Link
- Structural steel
- Area D and E Bathrooms
- Start installing plumbing fixtures and painting
- Old Concession Stand
- Ceiling and floor
- Lower Level Area F (Old locker rooms, new weight room)
- Continue interior masonry walls
- 2nd and 3rd level science rooms
- Mechanical and electrical rough-ins
- Old Special Ed./New Athletics Commons
- Ceiling work and painting
- New Athletic Corridor/Elevator
- Below grade masonry for elevator and storage room
- Start tiling in bathrooms
- Area A & B Art and Shop Classes
- Continue mechanical and electrical demolition
- Start wall framing
R-STEM Elementary
Completed week ending Friday, June 5, 2020:
- Wall framing in Special Education suite.
- Electrical work in Special Education suite.
- Set unit ventilators and connections in Music suite.
- Hydronic piping in Special Education and Music suite.
- Set pre-kindergarten unit ventilator.
- Drywall work in pre-kindergarten classroom.
- Abatement in boiler room and tunnel areas.
Planned week ending Friday, June 12, 2020:
- Finish in wall electrical work in Special Education Suite.
- Hydronic piping in Special Education and Music suite.
- Drywall work in Special Education and Music suite.
- Ceiling grid work in main level corridors.
- Bathroom tile work in pre-kindergarten classroom.
- Start demo work in kitchen area.
- Abatement in boiler room and tunnel areas.
Dual Language
Completed week ending Friday, June 5, 2020:
- Punch list items continue to be addressed.
- Continued to address mechanical/HVAC test and balance deficiencies.
- Contractors worked to address action items on the Commissioning Corrective Action Log.
Planned week ending Friday, June 12, 2020:
- Continue to address punch list items.
- Continue testing and balancing of the mechanical/HVAC system.
- ICS commissioning continued commissioning of the mechanical and HVAC systems.