ICS Weekly Report: June 5, 2020

ICS Weekly Report: June 5, 2020

*This report is submitted from ICS on a weekly basis.

Centennial Elementary

Completed week ending Friday, June 5, 2020:

  • Electrical connection cabinet placed on the exterior prefabricated pad.
  • Electrical main switchboard cabinet installed.
  • Wall finishes completed in the Special Ed. Suite.
  • Began acoustical ceiling grid install in the Special Ed. Suite.
  • Began concrete slab saw-cutting in the Boiler Room.
  • Began painting in the classrooms and corridors.
  • Completed metal stud framed walls in the Resource/Flex Classrooms (Area A).

Planned week ending Friday, June 12, 2020:

  • Complete concrete slab saw-cutting in the Boiler Room.
  • Continue above ceiling mechanical and electrical as well as underground electrical in the Media Center.
  • Continue acoustical ceiling grid installation in the Special Ed. Suite.
  • Continue mechanical and electrical rough-in in the Resource area.
  • Continue wall finishes throughout the classrooms and corridors.

Middle School

Completed week ending Friday, June 5, 2020:

  • Ductwork demolition on 2nd and 3rd floor.
  • Demolition of walls and soffits on 3rd floor.
  • Framing walls and soffits on 2nd floor stairwell entrances.
  • Mechanical and electrical rough ins in 2nd floor classrooms.
  • Wall framing and drywall work in Media Center.

Planned week ending Friday, June 12, 2020:

  • Removal and demolition of classroom louvers.
  • Continue framing walls and soffits on 2nd floor stairwell entrances.
  • Continue mechanical and electrical rough-ins in 2nd floor classrooms.
  • Wall framing and drywall work in Media Center.
  • Start mechanical and electrical rough-ins on 3rd floor.
  • Start framing walls and soffits on 3rd floor stairwell entrances.

Sheridan Hills Elementary

Completed week ending Friday, June 5, 2020:

  • Completed Level 2 C wing demolition.
  • Abatement contractor continued flooring and insulation removal in the Level 1 restrooms.
  • Completed architectural demo in the Level 1 restrooms.
  • Completed acoustical ceiling demolition in the Level 1 corridors.
  • Continued above ceiling mechanical and electrical rough-in the Level 2 C wing.
  • Begin masonry and hollow metal frame demo on Level 1.

Planned week ending Friday, June 12, 2020:

  • Complete excavation for footings and foundations at the Front Entrance expansion.
  • Begin footings and foundations at the Front Entrance expansion.
  • Continue mechanical and electrical rough-in in Level 2 C wing.
  • Continue mechanical and electrical rough-in in the future Front Admin Office.
  • Demo acoustical ceilings in the existing Admin Office.

Richfield High School

Completed week ending Friday, June 5, 2020:

  • Boiler Room
    • Continued mechanical and electrical connections of the boilers
  • Area P Link
    • Finished exterior wall and removed scaffolding
  • Area D and E Bathrooms
    • Finished tile work
  • Old Concession Stand
    • Ductwork and ceiling work
    • Old Board Room
    • Punch list work and cleaning
  • Lower Level Area F (Old locker rooms, new weight room)
    • Mechanical and electrical rough-ins
    • Build interior masonry walls
    • Wall sawing Set door and frames
  • 2nd and 3rd level science rooms
    • Mechanical and electrical rough-ins
  • Old Special Ed./New Athletics Commons
    • Drywall work
    • Painting and ceiling installation
  • New Athletic Corridor/Elevator
    • Footings and masonry walls for elevator and storage room
  • Area A & B Art and Shop Classes
    • Demolition

Planned week ending Friday, June 12, 2020:

  • Boiler Room
    • Continue mechanical and electrical connections of the boilers
  • Area P Link
    • Structural steel
  • Area D and E Bathrooms
    • Start installing plumbing fixtures and painting
  • Old Concession Stand
    • Ceiling and floor
  • Lower Level Area F (Old locker rooms, new weight room)
    • Continue interior masonry walls
  • 2nd and 3rd level science rooms
    • Mechanical and electrical rough-ins
  • Old Special Ed./New Athletics Commons
    • Ceiling work and painting
  • New Athletic Corridor/Elevator
    • Below grade masonry for elevator and storage room
    • Start tiling in bathrooms
  • Area A & B Art and Shop Classes
    • Continue mechanical and electrical demolition
    • Start wall framing

R-STEM Elementary

Completed week ending Friday, June 5, 2020:

  • Wall framing in Special Education suite.
  • Electrical work in Special Education suite.
  • Set unit ventilators and connections in Music suite.
  • Hydronic piping in Special Education and Music suite.
  • Set pre-kindergarten unit ventilator.
  • Drywall work in pre-kindergarten classroom.
  • Abatement in boiler room and tunnel areas.

Planned week ending Friday, June 12, 2020:

  • Finish in wall electrical work in Special Education Suite.
  • Hydronic piping in Special Education and Music suite.
  • Drywall work in Special Education and Music suite.
  • Ceiling grid work in main level corridors.
  • Bathroom tile work in pre-kindergarten classroom.
  • Start demo work in kitchen area.
  • Abatement in boiler room and tunnel areas.

Dual Language

Completed week ending Friday, June 5, 2020:

  • Punch list items continue to be addressed.
  • Continued to address mechanical/HVAC test and balance deficiencies.
  • Contractors worked to address action items on the Commissioning Corrective Action Log.

Planned week ending Friday, June 12, 2020:

  • Continue to address punch list items.
  • Continue testing and balancing of the mechanical/HVAC system.
  • ICS commissioning continued commissioning of the mechanical and HVAC systems.
First page of the PDF file: ICS_Weekly_Project_Update06-05-20