ICS Weekly Report: September 17, 2021

ICS Weekly Report: September 17, 2021

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Sheridan Hills Elementary

Completed week ending Friday,  September 17, 2021

  • Kitchen
    • Continued remaining work in the Kitchen.
    • Conducted City and Health Dept. final inspections which resulted in items that are being corrected.
  • Site
    • Formed and poured the exterior concrete stairs at the Gym exit.
  • General
    • Resumed testing and balancing of the HVAC systems.
    • All-State continued security and surveillance programming.

Planned week ending Friday, September 24, 2021

  • Kitchen
    • Correct/complete City and Health Dept. inspection items.
    • Conduct Health Dept. re-inspection.
    • Wold to conduct punchlist walkthrough.
    • Staff to continue moving into the Kitchen.
  • Site
    • Install Gym exit stair handrail and backfill Gym exit. 

Richfield Middle School

Completed week ending Friday, September 17, 2021

  • Punchlist and progress cleaning in Best Buy Teen Tech Center
  • Delivery and installation of backordered soft seating furniture
  • Finished auditorium HVAC hydronic re-piping and started clearing out auditorium foyer

Planned week ending Friday, September 24, 2021

  • Install doors in Best Buy Teen Tech Center
  • Insulate auditorium HVAC hydronic re-piping

Central Education Center

Completed week ending Friday, September 17, 2021

  • Completed work associated with the building cooling system in preparation for systems start-up on 9/23.
  • Complete heating system piping in the tunnels.
  • All-State completed programming the access control (security).
  • Completed Owner training on the new fire alarm system.
  • Completed Prep room painting.

Planned week ending Friday, September 24, 2021

  • Chilled water system cleaning/flushing and filling.
  • Continue heating water system piping in the Boiler Room.
  • All-State to continue programming of the camera system (surveillance).
  • Contractors to continue addressing punchlist items.