*This report is submitted from ICS on a weekly basis.
Centennial Elementary
Completed week ending Friday, June 12, 2020:
- Completed Boiler Room slab saw-cutting and removal.
- Completed Boiler Room concrete housekeeping pads.
- Completed the demo and removal of the existing Kitchen slab in preparation for underground rough-in.
- Continued above ceiling mechanical / electrical rough-in in the new Media Center.
- Completed demolition in the Main Entry vestibule.
- Completed ceiling grid installation in the Special Ed. Suite.
Planned week ending Friday, June 19, 2020:
- Begin Kitchen underground plumbing rough-in.
- Complete metal stud wall framing in the Media Center.
- Continue mechanical / electrical ceiling finishes in the Special Ed. Suite.
- Resume concrete slab infills.
- Continue painting in the corridors and classrooms.
Richfield Middle School
Completed week ending Friday, June 12, 2020:
- Removal and demolition of classroom louvers
- Built art kiln room walls
- Plumbing for main level staff bathrooms
- Continue framing walls and soffits on 2nd floor stairwell entrances
- Continue mechanical and electrical rough ins in 2nd floor classrooms
- Wall framing and drywall work in Media Center
- Start mechanical and electrical rough ins on 3rd floor
- Start framing walls and soffits on 3rd floor stairwell entrances
- Wall framing special education suites on 3rd floor
Planned week ending Friday, June 19, 2020:
- Framing walls for art and health classroom along with shared storage
- Mechanical rough ins for main level staff bathrooms
- Installing unit ventilators on 2nd and 3rd floor classrooms
- Drywall work in Media Center
- Continue framing walls and soffits on 3rd floor stairwell entrances
- Mechanical and electrical rough ins for 3rd floor
Sheridan Hills Elementary
Completed week ending Friday, June 12, 2020:
- Started digging the New Main Entry addition excavation.
- Started mechanical and electrical rough-in in the new Admin Office.
- Continued demolition in the existing Admin Office.
- Continued flooring removal by abatement contractor.
- Continued underground plumbing throughout the building.
- Continued above ceiling mechanical and electrical rough-in the Level 2 classrooms and corridor.
Planned week ending Friday, June 19, 2020:
- Complete the Main Entry addition excavation.
- Begin Main Entry addition footings and foundations.
- Continue mechanical and electrical rough-in in the new Admin Office.
- Continue demolition efforts in the existing Admin Office.
- Continue underground plumbing rough-in and begin slab infills.
- Continue flooring and insulation removals by abatement contractor.
Richfield High School
Completed week ending Friday, June 12, 2020:
- Boiler Room
- Continue mechanical and electrical connections of the boilers
- Area P Link
- Structural steel
- Area D and E Bathrooms
- Start installing plumbing fixtures and painting
- Old Concession Stand
- Ceiling and floor
- Lower Level Area F (Old locker rooms, new weight room)
- Continue interior masonry walls
- 2nd and 3rd level science rooms
- Mechanical and electrical rough ins
- Old Special Ed,/New Athletics Commons
- Ceiling work and painting
- Wall framing
- Drywall columns
- New Athletic Corridor/Elevator
- Below grade masonry for elevator and storage room
- Area A & B Art and Shop Classes
- Continue mechanical and electrical demolition
- Start wall framing
Planned week ending Friday, June 19, 2020:
- Boiler Room
- Continue mechanical and electrical connections of the boilers
- Area P Link
- Continue steel and roof deck erection
- Demolition of entrances on all three levels
- Roof blocking
- Area D and E Bathrooms
- Toilet partitions and accessories in area D
- Floor and wall tiling in area E
- Old Concession Stand
- Flooring
- Punchlist and final clean
- Lower Level Area F (Old locker rooms, new weight room)
- Continue masonry walls
- Mechanical and electrical rough ins
- 2nd and 3rd level science rooms
- Mechanical and electrical rough ins
- Old Special Ed,/New Athletics Commons
- Continue wall framing
- Mechanical electrical rough ins o New Athletic Corridor/Elevator
- Below grade masonry and backfill dirt on west side
- East side excavation and footings
- Tiling bathrooms
- Area A & B Art, FACS and Shop Classes
- Wall framing
- Mechanical and electrical rough ins.
R-STEM Elementary
Completed week ending Friday, June 12, 2020:
- Finish in wall electrical work in Special Education Suite
- Hydronic piping in Special Education and Music suite
- Drywall work in Special Education and Music suite
- Ceiling grid work in main level corridors
- Bathroom tile work in pre-kindergarten classroom
- Started demo work in kitchen area
- Abatement in boiler room and tunnel areas
Planned week ending Friday, June 19, 2020:
- Set and connect unit ventilators in Music Suite
- Finish drywall work in Special Education and Music suite
- Start wall and floor tile in Special Education Suite shower/bathroom
- Start painting Special Education and Music suite
- Continue ceiling grid in corridors
- Plumbing fixtures in pre-kindergarten restroom
- Start ceiling in pre-kindergarten restroom
- Kitchen dishwasher underground work
- Kitchen dishwasher wall framing
Richfield Dual Language School
Completed week ending Friday, June 12, 2020:
- Punch list items continue to be addressed.
- Continued to address mechanical/HVAC test and balance deficiencies.
- Contractors worked to address action items on the Commissioning Corrective Action Log.
Planned week ending Friday, June 19, 2020:
- Continue to address punch list items.
- Continue testing and balancing of the mechanical/HVAC system.
- ICS Commissioning continued commissioning of the mechanical and HVAC systems.