ICS Weekly Report: June 12, 2020

ICS Weekly Report: June 12, 2020

*This report is submitted from ICS on a weekly basis.

Centennial Elementary

Completed week ending Friday, June 12, 2020:

  • Completed Boiler Room slab saw-cutting and removal.
  • Completed Boiler Room concrete housekeeping pads.
  • Completed the demo and removal of the existing Kitchen slab in preparation for underground rough-in.
  • Continued above ceiling mechanical / electrical rough-in in the new Media Center.
  • Completed demolition in the Main Entry vestibule.
  • Completed ceiling grid installation in the Special Ed. Suite. 

Planned week ending Friday, June 19, 2020:

  • Begin Kitchen underground plumbing rough-in.
  • Complete metal stud wall framing in the Media Center.
  • Continue mechanical / electrical ceiling finishes in the Special Ed. Suite.
  • Resume concrete slab infills.
  • Continue painting in the corridors and classrooms. 

Richfield Middle School

Completed week ending Friday, June 12, 2020:

  • Removal and demolition of classroom louvers
  • Built art kiln room walls
  • Plumbing for main level staff bathrooms
  • Continue framing walls and soffits on 2nd floor stairwell entrances
  • Continue mechanical and electrical rough ins in 2nd floor classrooms
  • Wall framing and drywall work in Media Center
  • Start mechanical and electrical rough ins on 3rd floor
  • Start framing walls and soffits on 3rd floor stairwell entrances
  • Wall framing special education suites on 3rd floor

Planned week ending Friday, June 19, 2020:

  • Framing walls for art and health classroom along with shared storage
  • Mechanical rough ins for main level staff bathrooms
  • Installing unit ventilators on 2nd and 3rd floor classrooms 
  • Drywall work in Media Center
  • Continue framing walls and soffits on 3rd floor stairwell entrances
  • Mechanical and electrical rough ins for 3rd floor 

Sheridan Hills Elementary

Completed week ending Friday, June 12, 2020:

  • Started digging the New Main Entry addition excavation.
  • Started mechanical and electrical rough-in in the new Admin Office.
  • Continued demolition in the existing Admin Office.
  • Continued flooring removal by abatement contractor.
  • Continued underground plumbing throughout the building.
  • Continued above ceiling mechanical and electrical rough-in the Level 2 classrooms and corridor.

Planned week ending Friday, June 19, 2020:

  • Complete the Main Entry addition excavation.
  • Begin Main Entry addition footings and foundations.
  • Continue mechanical and electrical rough-in in the new Admin Office.
  • Continue demolition efforts in the existing Admin Office.
  • Continue underground plumbing rough-in and begin slab infills.
  • Continue flooring and insulation removals by abatement contractor. 

Richfield High School

Completed week ending Friday, June 12, 2020:

  • Boiler Room
    • Continue mechanical and electrical connections of the boilers
  • Area P Link
    • Structural steel
  • Area D and E Bathrooms
    • Start installing plumbing fixtures and painting
  • Old Concession Stand
    • Ceiling and floor
  • Lower Level Area F (Old locker rooms, new weight room)
    • Continue interior masonry walls
  • 2nd and 3rd level science rooms
    • Mechanical and electrical rough ins
  • Old Special Ed,/New Athletics Commons
    • Ceiling work and painting
    • Wall framing
    • Drywall columns
  • New Athletic Corridor/Elevator
    • Below grade masonry for elevator and storage room
  • Area A & B Art and Shop Classes
    • Continue mechanical and electrical demolition
    • Start wall framing 

Planned week ending Friday, June 19, 2020:

  • Boiler Room
    • Continue mechanical and electrical connections of the boilers
  • Area P Link
    • Continue steel and roof deck erection
    • Demolition of entrances on all three levels
    • Roof blocking
  • Area D and E Bathrooms
    • Toilet partitions and accessories in area D
    • Floor and wall tiling in area E
  • Old Concession Stand
    • Flooring
    • Punchlist and final clean
  • Lower Level Area F (Old locker rooms, new weight room)
    • Continue masonry walls
    • Mechanical and electrical rough ins
  • 2nd and 3rd level science rooms
    • Mechanical and electrical rough ins
  • Old Special Ed,/New Athletics Commons
    • Continue wall framing
    • Mechanical electrical rough ins o New Athletic Corridor/Elevator 
    • Below grade masonry and backfill dirt on west side
    • East side excavation and footings
    • Tiling bathrooms
  • Area A & B Art, FACS and Shop Classes
    • Wall framing
    • Mechanical and electrical rough ins. 

R-STEM Elementary

Completed week ending Friday, June 12, 2020:

  • Finish in wall electrical work in Special Education Suite
  • Hydronic piping in Special Education and Music suite
  • Drywall work in Special Education and Music suite
  • Ceiling grid work in main level corridors
  • Bathroom tile work in pre-kindergarten classroom
  • Started demo work in kitchen area
  • Abatement in boiler room and tunnel areas 

Planned week ending Friday, June 19, 2020:

  • Set and connect unit ventilators in Music Suite
  • Finish drywall work in Special Education and Music suite
  • Start wall and floor tile in Special Education Suite shower/bathroom
  • Start painting Special Education and Music suite
  • Continue ceiling grid in corridors
  • Plumbing fixtures in pre-kindergarten restroom
  • Start ceiling in pre-kindergarten restroom
  • Kitchen dishwasher underground work
  • Kitchen dishwasher wall framing 

Richfield Dual Language School

Completed week ending Friday, June 12, 2020:

  • Punch list items continue to be addressed.
  • Continued to address mechanical/HVAC test and balance deficiencies.
  • Contractors worked to address action items on the Commissioning Corrective Action Log. 

Planned week ending Friday, June 19, 2020:

  • Continue to address punch list items.
  • Continue testing and balancing of the mechanical/HVAC system.
  • ICS Commissioning continued commissioning of the mechanical and HVAC systems. 