ICS Weekly Report: July 31, 2020

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Centennial Elementary

Completed week ending Friday, July 31, 2020

  • Chiller unit was hoisted by crane into the enclosure.
  • Completed the tile work in the Area A multi-user Toilet Rooms.
  • Continued casework installation in the classrooms.
  • Completed drywall installation in the Admin and Nurse areas.
  • Began installing markerboards in the perimeter classrooms.
  • Continued mechanical piping rough-in in the Boiler Room.

Planned week ending Friday, August 7, 2020

  • Complete the installation of plumbing fixtures in the Area A multi-user Toilet Rooms.
  • Complete drywall installation in the Area B multi-user Toilet Rooms and begin tile work.
  • Begin carpet installation in the Area A perimeter classrooms.
  • Begin painting walls in the Media Center and Admin/Nurse areas.
  • Begin tile work in the Admin/Nurse area.
  • Install coiling door and operable glass partitions in the Media Center.
  • Continue casework installation throughout the building.

Richfield Middle School

Completed week ending Friday, July 31, 2020

  • Continued painting on third level
  • Continued installing ceiling grid and light fixtures on third and second level corridors
  • Started installing casework on third and second level
  • Continued flooring installation on third level
  • Tiled walls in staff bathrooms and resource areas on third level
  • Started flooring in classrooms on second level
  • Started installing ceiling grid on main level

Planned week ending Friday, August 7, 2020

  • Continue painting and unit ventilator installation on third level and second level
  • Continue wall tile on third level
  • Continue classroom carpet on third and second level
  • Start tiling staff bathrooms on second level
  • Mechanical and electrical rough ins on main level
  • Install structural steel for roof top units
  • Casework installation throughout

Sheridan Hills Elementary

Completed week ending Friday, July 31, 2020

  • Completed the structural steel at the Front Entry addition.
  • Completed the new concrete ramp at the Front Entry corridor.
  • Admin area drywall hanging and taping is nearing completion.
  • C wing Level 2 classrooms wall painting and ceiling grid installation is complete.
  • Started tile work in the C wing Level 2 multi-user Toilet Rooms.
  • Started painting wall finishes in the SPED Suite.

Planned week ending Friday, August 7, 2020

  • Complete painting walls in the SPED Suite.
  • Complete ceiling grid installation in the SPED Suite.
  • Begin install mechanical and electrical ceiling finishes i.e. lights, grilles and diffusers in the C wing Level 2 classrooms.
  • Continue tile work in the C wing Level 2 multi-user Toilet Rooms.
  • Begin painting wall finishes in the Admin area.

Richfield High School

Completed week ending Friday, July 31, 2020

  • Boiler Room
    • Continued boiler piping
  • Area P Link
    • Mechanical and electrical rough ins on all levels
    • Continued exterior finish system
    • Continued interior wall framing
    • Set rooftop HVAC units on roof
  • Area D Main Lower Level Classroom
    • Installed flooring
  • Lower Level Area F Dance Studio and Weight Room
    • Mechanical and Electrical Testing
  • 2nd and 3rd level science rooms
    • Continued casework and plumbing installation
  • New Athletics Commons and concessions
    • Ceiling grid installation
    • Installed mechanical and electrical finishes
    • Fin tube installation
  • New Athletic Corridor/Elevator
    • Above grade masonry
  • Main Gym
    • Continued wood flooring installation
  • Area A & B Art, FACS and Shop Classes
    • Flooring installed out in corridors
    • Casework Installation
    • Mechanical and electrical finishes
  • Loading Dock
    • Poured concrete walls and rebar
    • Install trench drains
  • Exterior Work
    • Irrigation at front entrance
    • Installed pavers and planter at Courtyard

Planned week ending Friday, August 7, 2020

  • Boiler Room
    • Continue boiler connections
  • Area P Link
    • Continue Mechanical and electrical rough ins
    • Continue exterior finish system
  • Lower Level Area F Dance Studio and Weight Room
    • Start ceiling grids in corridors
  • 2nd and 3rd level science rooms
    • Continue casework and plumbing installation
  • New Athletics Commons and concessions
    • Wall tile work
    • Continue ceiling
    • Continue fin tube installation
  • New Athletic Corridor/Elevator
    • Above grade masonry
  • Main Gym
    • Continue wood flooring installation
  • Area A & B Art, FACS and Shop Classes
    • Continue casework installation
    • Continue flooring and ceilings
    • Mechanical and electrical finishes
  • Loading Dock
    • Pour concrete walls and dock level
  • Exterior Work
    • District Parking Lot Grading
    • Continue irrigation at front entrance

Richfield STEM Elementary

Completed week ending Friday, July 31, 2020

  • Install tack wall in kindergarten rooms
  • Continued furniture installation
  • Installed ceiling pads in vestibule and front lobby
  • Connected dishwashing equipment
  • Continued boiler room mechanical connections
  • Punchlist Kindergarten and Pre-kindergarten classrooms
  • Flooring at entrance

Planned week ending Friday, August 7, 2020

  • Finish flooring at main entrance
  • Continue dishwash equipment connections
  • Start ceiling grid in kitchen and dishwash area
  • Sprinkler work in dishwash area
  • Continue boiler room work
  • Install sinks at Pre-kindergarten classrooms
  • Exterior sod restoration
  • Continue punch list

Richfield Dual Language School

Completed week ending Friday, July 31, 2020

  • Contractors continued working to address punch list items.
  • ICS Commissioning continued performing the commissioning of the building’s mechanical and HVAC systems.

Planned week ending Friday, August 7, 2020

  • Contractors to continue working to address punch list items.
  • Contractors to continue working to address items noted on the commissioning corrective action log.