ICS Weekly Report: January 8, 2021

ICS Weekly Report: January 8, 2021

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Richfield High School

Completed week ending Friday, January 8, 2021

  • Mirrors installed in dance room and weight room
  • Continued punch list items
  • Continued testing, balancing, and commissioning

Planned week ending Friday, January 15, 2021

  • Delivery and installation of wall pads in wrestling room
  • Clear our construction material and clean out auxiliary gyms
  • Continue punch list items
  • Continue testing, balancing, and commissioning

Centennial Elementary

Completed week ending Friday, January 8, 2021

  • Contractors continued working to address punch list and IEA Commissioning log items.
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems.
  • Rebate applications are being completed for submission.

Planned week ending Friday, January 15, 2021

  • Contractors to continue working to address punch list and IEA Commissioning log items.
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems.
  • Utility rebate applications and required attachments to continue being pulled together.

Sheridan Hills Elementary

Completed week ending Friday, January 8, 2021

  • Contractors continued working to address punch list and IEA Commissioning log items.
  • IEA Commissioning continued the commissioning of the mechanical/HVAC systems.
  • Continued hydronic piping runs to the new chiller.
  • Rebate applications are being completed for submission.

Planned week ending January 15, 2021

  • Contractors to continue to address punch list and IEA Commissioning log items.
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems.
  • Continue installing hydronic piping runs to the new chiller unit and making final connections.
  • Utility rebate applications and required attachments to continue being pulled together.

Richfield Middle School

Completed week ending Friday, January 8, 2021

  • Phase 2 New Conference Room and Staff Lounge  
    • Punch list and sink installation
  • Phase 2 FACS Lab
    • Punch list
  • Phase 3 Third Floor Restrooms
    • Installed toilet partitions
  • Phase 3 Second Floor Restrooms
    • Installed tiling in north restroom
    • Wall framing and wood blocking in south restroom
  • Phase 3 Existing Administration Offices
    • Mechanical, electrical, plumbing rough ins
    • Continued wall framing
  • Phase 3 Existing Music Suite
    • Continued demolition
    • Mechanical, electrical, plumbing rough ins
    • Tiered floor infills with insulation

Planned week ending Friday, January 15, 2021

  • Phase 2 New Conference Room and Staff Lounge
    • Turn over to school
  • Phase 2 FACS Lab
    • Punch list
  • Phase 3 Third Floor Restrooms
    • Finish ceiling
  • Phase 3 Second Floor Restrooms
    • Sheetrocking in south restroom
    • Start installing tiling in north restroom
  • Phase 3 Existing Administration Offices
    • Mechanical, electrical, plumbing rough ins
    • Finish wall framing
    • Wood backing installation in walls
    • Start sheet rocking walls
  • Phase 3 Existing Music Suite
    • Mechanical, electrical, plumbing rough ins
    • Pour in concrete floors at tiered areas
    • Start mechanical and electrical rough ins

Richfield STEM Elementary

Completed week ending Friday, January 8, 2021

  • Received final occupancy certificate
  • Walkthrough with administration and custodial staff on punch list occurred
  • Continued testing, balancing, and commissioning

Planned week ending Friday, January 15, 2021

  • Continue testing, balancing, and commissioning
  • All State to come on site to resolve minor punch list items

Richfield Dual Language School

Completed week ending Friday, January 8, 2021

  • Contractors continued working to address items noted on the commissioning corrective action log.
  • Contractors have addressed all issues identified during the 11-month warranty walkthrough.
  • Completed the final building inspection and closed all permits.

Planned week ending Friday, January 15, 2021

  • Contractors to continue working to address items noted on the commissioning corrective action log.

Central Education Center

Completed week ending January 8, 2021

  • The School Board approved the Contractor Award Recommendation on 1/4/2021.
  • The contract has been issued to Rochon Corporation.
  • Continued preconstruction work with Rochon and moving coordination.

Planned week ending Friday, January 15, 2021

  • Continue preconstruction work with Rochon and moving coordination.
  • Scheduling of the Preconstruction meeting to take place.
  • ICS to present the packing and moving plan to the building staff on 1/13.