District News
ICS Weekly Report: February 12, 2021
Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page.
*This report is submitted from ICS on a weekly basis.
Richfield High School
Completed week ending Friday, February 19, 2021
- Delivery of interior vestibule doors at the main gym entrance, and start of installation
- Continued punch list items as well as ICS verification of completion of the punch list items
- Continued testing, balancing, and commissioning
Planned week ending Friday, February 26, 2021
- ICS Commissioning will be on-site to review open commissioning list items for completion
- Contractors to continue working to address items noted on the commissioning corrective action log
Centennial Elementary
Completed week ending Friday, February 19, 2021
- IEA Commissioning to continue commissioning the mechanical/HVAC systems
- Contractors continued working IEA Commissioning log items
Planned week ending Friday, February 26, 2021
- Contractors to continue working to address IEA Commissioning log items
- IEA Commissioning to continue commissioning the mechanical/HVAC systems
Sheridan Hills Elementary
Completed week ending Friday, February 19, 2021
- IEA Commissioning continued the commissioning of the mechanical/HVAC systems
- Contractors continued working to address punch list and IEA Commissioning log items
Planned week ending Friday, February 26, 2021
- IEA Commissioning to continue commissioning the mechanical/HVAC systems
- Contractors continue to address punch list and IEA Commissioning log items
Richfield Middle School
Completed week ending Friday, February 19, 2021
- General
- Short power outage for electrical connections
- Third Floor Restrooms
- Turned over to school
- Second Floor Restrooms
- Punch list
- Final cleaned
- First Floor Restrooms
- Sheet rocked north bathrooms
- Started tiling in south bathrooms
- Existing Administration Offices/New Special Education Suite
- Continued painting
- Continued ceiling grid
- Finished soffits in corridor
- Existing Music Suite/New Design Lab
- Carpeted band room
- Continued mechanical and electrical rough ins
- Wood Shop/New Administration/Fab Lab
- Continued mechanical rough ins
- Continued wall framing
Planned week ending Friday, February 26, 2021
- Second Floor Restrooms
- Turn over to school
- First Floor Restrooms
- Start tiling north restrooms
- Finish tiling south restrooms
- Start installing toilet fixtures and toilet partitions in south restrooms
- Existing Administration Offices/New Special Education Suite
- Finish ceilings
- Existing Music Suite/New Design Lab
- Install floor insulation at tiered music room
- Pour concrete floor in music room
- Continue mechanical and electrical rough ins
- Wood Shop/New Administration/Fab Lab
- Finish wall framing
- Start sheet rocking
- Continue mechanical and electrical rough ins
Richfield STEM Elementary
Completed week ending Friday, February 19, 2021
- Review operation and maintenance manuals
Planned week ending Friday, February 26, 2021
- ICS to continue commissioning
Richfield Dual Language School
Completed week ending Friday, February 19, 2021
- Contractors continued working to address items noted on the commissioning corrective action log
Planned week ending Friday, February 26, 2021
- ICS Commissioning will be on-site to review open commissioning list items for completion
- Contractors to continue working to address items noted on the commissioning corrective action log
Central Education Center
Completed week ending Friday, February 19, 2021
- Material submittals are being uploaded to Procore for review and approval
- Conducted the weekly Construction Progress/Coordination meeting
- All Furniture (moving coming) completed the move-out of district items out of the Phase 1 construction area
- District IT facilitated moving staff technology components out of the Phase 1 construction area to their temporary office locations
Planned week ending Friday, February 26, 2021
- Continue with weekly Construction Progress/Coordination meetings
- Continue receiving and reviewing material submittals
- Rochon (General Contractor) to mobilize on-site and construct temporary partitions and begin demolition
- Abatement contractor to mobilize on-site to setup containment areas and begin their material removals