Richfield High School

Completed week ending Friday, February 19, 2021

  • Delivery of interior vestibule doors at the main gym entrance, and start of installation
  • Continued punch list items as well as ICS verification of completion of the punch list items
  • Continued testing, balancing, and commissioning

Planned week ending Friday, February 26, 2021

  • ICS Commissioning will be on-site to review open commissioning list items for completion
  • Contractors to continue working to address items noted on the commissioning corrective action log

Centennial Elementary

Completed week ending Friday, February 19, 2021

  • IEA Commissioning to continue commissioning the mechanical/HVAC systems
  • Contractors continued working IEA Commissioning log items

Planned week ending Friday, February 26, 2021

  • Contractors to continue working to address IEA Commissioning log items
  • IEA Commissioning to continue commissioning the mechanical/HVAC systems

Sheridan Hills Elementary

Completed week ending Friday, February 19, 2021

  • IEA Commissioning continued the commissioning of the mechanical/HVAC systems
  • Contractors continued working to address punch list and IEA Commissioning log items

Planned week ending Friday, February 26, 2021

  • IEA Commissioning to continue commissioning the mechanical/HVAC systems
  • Contractors continue to address punch list and IEA Commissioning log items

Richfield Middle School

Completed week ending Friday, February 19, 2021

  • General
    • Short power outage for electrical connections
  • Third Floor Restrooms
    • Turned over to school
  • Second Floor Restrooms
    • Punch list
    • Final cleaned
  • First Floor Restrooms
    • Sheet rocked north bathrooms
    • Started tiling in south bathrooms
  • Existing Administration Offices/New Special Education Suite
    • Continued painting
    • Continued ceiling grid
    • Finished soffits in corridor
  • Existing Music Suite/New Design Lab
    • Carpeted band room
    • Continued mechanical and electrical rough ins
  • Wood Shop/New Administration/Fab Lab
    • Continued mechanical rough ins
    • Continued wall framing

Planned week ending Friday, February 26, 2021

  • Second Floor Restrooms
    • Turn over to school
  • First Floor Restrooms
    • Start tiling north restrooms
    • Finish tiling south restrooms
    • Start installing toilet fixtures and toilet partitions in south restrooms
  • Existing Administration Offices/New Special Education Suite
    • Finish ceilings
  • Existing Music Suite/New Design Lab
    • Install floor insulation at tiered music room
    • Pour concrete floor in music room
    • Continue mechanical and electrical rough ins
  • Wood Shop/New Administration/Fab Lab
    • Finish wall framing
    • Start sheet rocking
    • Continue mechanical and electrical rough ins

Richfield STEM Elementary

Completed week ending Friday, February 19, 2021

  • Review operation and maintenance manuals

Planned week ending Friday, February 26, 2021

  • ICS to continue commissioning

Richfield Dual Language School

Completed week ending Friday, February 19, 2021

  • Contractors continued working to address items noted on the commissioning corrective action log

Planned week ending Friday, February 26, 2021

  • ICS Commissioning will be on-site to review open commissioning list items for completion
  • Contractors to continue working to address items noted on the commissioning corrective action log

Central Education Center

Completed week ending Friday, February 19, 2021

  • Material submittals are being uploaded to Procore for review and approval
  • Conducted the weekly Construction Progress/Coordination meeting
  • All Furniture (moving coming) completed the move-out of district items out of the Phase 1 construction area
  • District IT facilitated moving staff technology components out of the Phase 1 construction area to their temporary office locations

Planned week ending Friday, February 26, 2021

  • Continue with weekly Construction Progress/Coordination meetings
  • Continue receiving and reviewing material submittals
  • Rochon (General Contractor) to mobilize on-site and construct temporary partitions and begin demolition
  • Abatement contractor to mobilize on-site to setup containment areas and begin their material removals