ICS Weekly Report: September 11, 2020

ICS Weekly Report: September 11, 2020

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Richfield High School

Completed week ending Friday, September 11, 2020

  • General
    • Punch List
    • Cleaning
    • Furniture Installation
  • Boiler Room
    • Mechanical connections
  • Area P Link
    • Installed ceiling pad on main floor
    • Drywall shaft walls on 2nd and 3rd floor
    • Installed ceiling grid on 2nd floor
    • Started ceiling grid on 3rd floor
  • Lower Level Area F Dance Studio and Weight Room
    • Installed ceiling grid in multipurpose rooms
    • Installed glass in weight room and dance studio
    • Installed sub-base wood floor in dance studio
  • Area C 3rd level science rooms
    • Finish up plumbing
  • Area C 3rd level restrooms
    • Plumbing rough ins
  • New Athletic Corridor/Elevator
    • Started interior masonry walls
    • Installed floor decking
  • Main Gym
    • Installed floor transitions
  • Exterior Work
    • Landscaping throughout

Planned week ending Friday, September 18, 2020

  • General
    • Punch list
    • Testing, balancing, and commissioning of mechanical systems
  • Boiler Room
    • Mechanical connections to continue
  • Area P Link
    • Temporary window condition to be addressed
  • Lower Level Area F Dance Studio and Weight Room
    • Flooring installation to continue
  • Area C 3rd level science rooms
    • Plumbing rough-ins to be completed and gyp board install to begin
  • Area C 3rd level restrooms
    • Plumbing rough ins to be completed, gyp board install to begin
  • New Athletic Corridor/Elevator
    • Roofing to continue and interior work to continue
  • Exterior Work
    • Sod and landscaping throughout

Centennial Elementary

Completed week ending Friday, September 11, 2020

  • Completed minor issues noted by the MN Dept. of Health and the building official in the Kitchen and passed the re-inspection. Kitchen is now fully operational.
  • Completed the VCT patching in the area between the Kitchen and the Cafeteria.
  • Contractor completed their final cleaning efforts.
  • Contractors worked to complete punchlist items.
  • Continued working on boiler piping.

Planned week ending Friday, September 18, 2020

  • Contractor to continue working to address punchlist items.
  • Contractor to continue working through testing and balancing of the HVAC/mechanical equipment.
  • Continue boiler room piping efforts.
  • All State to continue installing security system components.

Sheridan Hills Elementary

Completed week ending Friday, September 11, 2020

  • Completed the storefront/glazing, exterior sheathing, air barrier and insulation at the Front Entry addition.
  • Completed the asphalt patching adjacent to the new concrete curb at the Front Entry.
  • Continued Lower Level Phase 2 mechanical piping and equipment setting.
  • Contractor worked to address punchlist items.
  • Contractor continued final cleaning efforts and worked to consolidate materials in the parking lot staging area.

Planned week ending Friday, September 18, 2020

  • Complete the brick work at the Front Entry addition.
  • Contractor to continue working to address punchlist items.
  • Contractor to continue working through testing and balancing of the HVAC/mechanical equipment.
  • All State to continue installing security system components.
  • Continue Phase 2 mechanical piping in the Lower Level.

Richfield Middle School

Completed week ending Friday, September 11, 2020

  • Phase 1 punch list
    • Mechanical diffusers in science rooms installed
    • Vinyl base in staff restroom corridors
    • Media Center furniture installation
  • Phase 2
    • Area D Special Education
      • Demolition
      • Wall framing for new classroom
      • Mechanical and electrical in new classroom
    • Restrooms
      • Plumbing Rough In work

Planned week ending Friday, September 18, 2020

  • Continue Phase 1 punch list
  • Phase 2
    • Area D Special Education
      • Drywall new classroom
      • Mechanical and electrical in new classroom
    • Restrooms
      • Wall and floor tile

Richfield STEM Elementary

Completed week ending Friday, September 11, 2020

  • Continue punch list
  • Boiler room mechanical work
  • Conducted 11-month warranty walk through for 2nd and 3rd level Phase 1 scope

Planned week ending Friday, September 18, 2020

  • Testing, balancing, and commissioning of mechanical systems
  • Remaining Punch List work to be completed – Tackable Wall Covering
  • Boiler room work

Richfield Dual Language School

Completed week ending Friday, September 11, 2020

  • ICS Commissioning continued performing the commissioning of the building’s mechanical and HVAC systems.
  • Contractors continued working to address items noted on the commissioning corrective action log.

Planned week ending Friday, September 18, 2020

  • ICS Commissioning to continue performing the commissioning of the building’s mechanical and HVAC systems.
  • Contractors to continue working to address items noted on the commissioning corrective action log.

Download PDF Report

ICS Weekly Project Report: September 11, 2020