ICS Weekly Report: July 24, 2020

ICS Weekly Report: July 24, 2020

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Centennial Elementary

Completed week ending Friday, July 24, 2020

  • Began casework installation in the classrooms.
  • Continued tile work in the multi-user Toilet Rooms.
  • Placed the concrete pad for the new chiller unit.
  • Continued painting in the classrooms.
  • Installed exhaust hoods in the Kitchen area.
  • Started setting mechanical equipment in the Boiler Room.

Planned week ending Friday, July 31, 2020

  • Set the new chiller unit in the chiller enclosure.
  • Begin door and hardware installation in the SPED Suite.
  • Continue classroom casework installation.
  • Complete tile work in the Area A multi-user Toilet Rooms.
  • Start acoustical ceiling grid installation in the Flex areas.
  • Complete drywall installation in the Media Center area.
  • Complete metal stud wall framing in the Kitchen and continue plumbing, mechanical and electrical rough-in in that area.

Richfield Middle School

Completed week ending Friday, July 24, 2020

  • Casework deliveries received for several areas
  • Roughed in art room display cases on main level
  • Finished drywall framing on second level
  • Started carpet installation in classrooms on third level
  • Started painting walls on first and third level
  • Installed structural steel on roof for mechanical equipment
  • Mechanical ductwork insulation installation in Special Education Suites
  • Installed ceiling grid on second and third floor corridors

Planned week ending Friday, July 31, 2020

  • Continue painting on third level
  • Continue installing ceiling grid on third and second level
  • Start installing casework on third and second level
  • Continue flooring installation on third level
  • Tile walls in staff bathrooms on third level
  • Start flooring in classrooms on second level
  • Start installing ceiling grid on main level

Sheridan Hills Elementary

Completed week ending Friday, July 24, 2020

  • Began setting unit ventilators in the Area C classrooms.
  • Complete hollow metal door and window frame installation in Area C.
  • Continued drywall installation in Area C and the new Admin Office areas.
  • Began structural steel erection at the Front Entry addition.
  • Completed waste and vent plumbing piping in Area A.

Planned week ending Friday, July 31, 2020

  • Complete drywall installation in Area C.
  • Begin making final mechanical connections to the unit ventilators.
  • Begin painting walls in Area C.
  • Begin acoustical ceiling grid installation in Area C.
  • Complete steel erection at the Front Entrance addition.
  • Complete concrete ramp at the Front Entry corridor.

Richfield High School

Completed week ending Friday, July 24, 2020

  • Boiler Room
    • Continued piping of boilers
  • Area P Link
    • Poured concrete on third floor
    • Mechanical and electrical rough in on first and second level
    • Continued exterior finish system
    • Started interior wall framing on second level
  • Area D Main Lower Level Classroom
    • Continued ceilings in classrooms and corridor
  • Lower Level Area F Dance Studio and Weight Room
    • Cleaned and assessed mechanical and electrical equipment due to water
  • 2nd and 3rd level science rooms
    • Continued casework and plumbing installation
  • New Athletics Commons and concessions
    • Started flooring in athletic commons
    • Started fiber reinforce wall finishes in concessions
  • New Athletic Corridor/Elevator
    • Continued above grade masonry
  • Main Gym
    • Continued wood flooring installation
  • Area A & B Art, FACS and Shop Classes
    • Painted walls in Art Rooms
  • Loading Dock
    • Poured concrete for foundation walls

Planned week ending Friday, July 31, 2020

  • Boiler Room
    • Continue boiler connections
  • Area P Link
    • Mechanical and electrical rough ins
    • Continue exterior finish system
    • Continue interior wall framing
  • Area D Main Lower Level Classroom
    • Install flooring
  • Lower Level Area F Dance Studio and Weight Room
    • Start ceiling grids in corridors
  • 2nd and 3rd level science rooms
    • Continue casework and plumbing installation
  • New Athletics Commons and concessions
    • Floor tile in concessions
    • Install mechanical and electrical finishes
    • Fin tube installation
  • New Athletic Corridor/Elevator
    • Above grade masonry
  • Main Gym
    • Continue wood flooring installation
  • Area A & B Art, FACS and Shop Classes
    • Casework Installation
    • Mechanical and electrical finishes
  • Loading Dock
    • Install trench drains
  • Exterior Work
    • Irrigation at front entrance

Richfield STEM Elementary

Completed week ending Friday, July 24, 2020

  • Installed flooring in Music and Special Education Suites
  • Classroom furniture delivered and installation began
  • Installed sinks in classrooms
  • Installed dishwashing equipment

Planned week ending Friday, July 31, 2020

  • Install tack wall in kindergarten rooms
  • Continue furniture installation
  • Install ceiling pads in vestibule and front lobby
  • Connect dishwashing equipment
  • Continue boiler room mechanical connections
  • Punchlist Kindergarten and Pre-kindergarten classrooms

Richfield Dual Language School

Completed week ending Friday, July 24, 2020

  • Contractors continued working to address punch list items.
  • ICS Commissioning continued performing the commissioning of the building’s mechanical and HVAC systems.

Planned week ending Friday, July 31, 2020

  • Contractors to continue working to address punch list items. Contractors to continue working to address items noted on the commissioning corrective action log.

Download PDF Report