Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page.
*This report is submitted from ICS on a weekly basis.
Richfield High School
Completed week ending Friday, April 2, 2021
- Walkthrough with LS Black to review punchlist completion and identify outstanding items.
Planned week ending Friday, April 9, 2021
- Work on closing out last change order
- Punchlist completion
- Installation of loading dock guardrails
Centennial Elementary
Completed week ending Friday, April 2, 2021
- Contractors continued working to address punch list and IEA Commissioning log items.
Planned week ending Friday, April 9, 2021
- IEA Commissioning to continue verifying completed commissioning log items.
Sheridan Hills Elementary
Completed week ending Friday, April 2, 2021
- Contractors continued working to address punch list and IEA Commissioning log items.
- Started masonry walls at the Kitchen/Receiving area addition.
Planned week ending Friday, April 9, 2021
- Contractors to continue to address punch list and IEA Commissioning log items.
- Continue CMU at the Kitchen/Receiving area addition.
Richfield Middle School
Completed week ending Friday, April 2, 2021
- First Floor Restrooms
- Punch list
- Existing Administration Offices/New Special Education Suite
- Punch list
- Installed casework
- Existing Music Suite/New Design Lab
- Installed ceiling grid and light fixtures
- Prepped floor for finishes
- Wood Shop/New Administration/Student Services/Fab Lab
- Abatement in new administration office
- Light demolition in administration office
- Painting in wood shop and student services
- Ceiling work in wood shop
Planned week ending Friday, April 9, 2021
- Existing Music Suite/New Design Lab
- Install flooring in choir room
- Install ceiling pads in choir room
- Final clean in choir room
- Wood Shop/New Administration/Student Services/Fab Lab
- Wall framing in new administration office
- Mechanical and electrical rough in at new administration office
Richfield STEM Elementary
Completed week ending Friday, April 2, 2021
- Punch list work (installed exterior light fixture)
- Reviewed Operations and Maintenance Manuals
- Commissioning continued
Planned week ending Friday, April 9, 2021
- Continue to review and approve Operations and Maintenance Manuals
- Continue commissioning
Richfield Community Education - Central Education Center
Completed week ending Friday, April 2, 2021
- Completed chimney demolition at the roof level.
- Completed concrete slab infills at underground plumbing trenches.
- Continued metal stud partition wall framing and hollow metal door frames in Areas A & D.
- Continued above ceiling mechanical and electrical rough-in in Areas A and D.
- Continue mechanical and electrical demolition in the Lower Level.
- Began in-wall plumbing rough-in in Area A.
- Completed demolition of the existing chiller enclosure walls.
Planned week ending Friday, April 9, 2021
- Continue mechanical and electrical demolition in the Lower Level.
- Continue in-wall mechanical and electrical rough-in in Areas A & D.
- Begin drywall hanging, taping, and sanding in Areas A & D.
- Begin roof openings for new mechanical equipment in Areas A & D.
- Begin excavation for chiller enclosure footings and foundations.