ICS Weekly Report: October 16, 2020

ICS Weekly Report: October 16, 2020

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Richfield High School

Completed week ending Friday, October 16, 2020

  • Boiler Room
    • Electrical and mechanical piping connections continued.
  • Area P Link
    • Casework installation
  • Lower Level Area F Dance Studio and Weight Room
    • Started weight room flooring
    • Vinyl base installation in multipurpose rooms and corridors
  • Area C 3rd level science rooms
    • Finish setting cabinets and tops in north classroom
  • Area C 3rd level restrooms
    • Started floor tiling
  • New Athletic Corridor/Elevator
    • Continued elevator installation
    • Continued mechanical and electrical rough ins

Planned week ending Friday, October 23, 2020

  • Boiler Room
    • Continue electrical and mechanical piping connections
  • Area P Link
    • Finish carpet flooring and casework installation
  • Lower Level Area F Dance Studio and Weight Room
    • Finish weight room flooring
  • Area C 3rd level science rooms
    • Finish setting cabinets and tops in south classroom
    • Start chemical resistant flooring
  • Area C 3rd level restrooms
    • Finish floor tile and start wall tile installation
  • New Athletic Corridor/Elevator
    • Continue elevator installation
    • Continue mechanical and electrical rough ins

Centennial Elementary

Completed week ending Friday, October 16, 2020

  • Contractors worked to complete punch list items.
  • Contractors corrected issues noted on the IEA Commissioning corrective action log.
  • Completed all boiler room piping and equipment installation. Boiler system has been inspected and is now operational.
  • Began cleaning and flushing the heating and cooling piping system.
  • Continued testing and balancing of the mechanical/HVAC system.
  • Completed the programming of the lighting controls.
  • All-State continued installing security system components.
  • Purchase order issued for the supply and install of window treatments.

Planned week ending Friday, October 23, 2020

  • Contractor to continue working to address punch list items.
  • Contractor to complete testing and balancing of the mechanical/HVAC systems.
  • All-State to complete the installation of all security system components.

Sheridan Hills Elementary

Completed week ending Friday, October 16, 2020

  • Continued working to address punch list items.
  • Continued Phase 2 mechanical piping in the Lower Level.
  • Backfilled the Kitchen/Receiving addition
  • Completed the new storm sewer piping and connection to existing manhole on W. 64th St.

Planned week ending Friday, October 23, 2020

  • Contractors to continue working to address punch list items.
  • Contractors to work to address deficiencies noted on the Testing and Balancing deficiencies checklist.
  • Continue Phase 2 mechanical piping in the Lower Level.
  • All State to complete the installation of all security system components.
  • Complete the asphalt patching and curb replacement on W. 64th St.
  • Begin excavation for the Chiller Enclosure addition.

Richfield Middle School

Completed week ending Friday, October 16, 2020

  • Phase 2 Area D Special Education/Link
    • Restroom plumbing rough ins continued
    • Ceiling grid and light installation
  • Phase 2 New Conference Room and Staff Lounge
    • Drywall mudding and taping
  • Phase 2 FACS Lab
    • Mechanical and electrical rough ins
  • Phase 2 Chiller Tower
    • Electrical transformer pad formed for concrete slab
    • Continued underground utilities
    • Started above grade masonry walls
  • Phase 3 Third Floor Restrooms
    • Mechanical and electrical rough ins to continue
    • Started wall framing

Planned week ending Friday, October 23, 2020

  • Phase 2 Area D Special Education/Link
    • Finish ceiling pad installation
    • Restroom tile installation
  • Phase 2 New Conference Room and Staff Lounge
    • Wall painting
    • Ceiling grid installation to begin
  • Phase 2 FACS Lab
    • Drywall installation and painting took place
  • Phase 2 Chiller Tower
    • Continue exterior CMU walls
    • Pour transformer concrete pads
  • Phase 3 Third Floor Restrooms
    • Drywall installation continued

Richfield STEM Elementary

Completed week ending Friday, October 16, 2020

  • Continued testing, balancing, and commissioning of mechanical systems

Planned week ending Friday, October 23, 2020

  • Furniture punch list items to be delivered and installed

Richfield Dual Language School

Completed week ending Friday, October 16, 2020

  • Contractors continued working to address items noted on the commissioning corrective action log.
  • Contractors worked to address issues identified during the 11-month warranty walkthrough.

Planned week ending Friday, October 23, 2020

  • Contractors to continue working to address items noted on the commissioning corrective action log.
  • Contractors to continue working to address issues identified during the 11-month warranty walkthrough.