ICS Weekly Report: October 9, 2020

ICS Weekly Report: October 9, 2020

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Richfield High School

Completed week ending Friday, October 9, 2020

  • Boiler Room
    • Started two of the four boilers
    • Continued mechanical connections
  • Area P Link
    • Installed ceiling pads
    • Started flooring in offices
    • Installed marker boards
  • Lower Level Area F Dance Studio and Weight Room
    • Ceiling pad installation in multipurpose rooms and corridors
  • Area C 3rd level science rooms
    • Set new cabinets and countertops
  • Area C 3rd level restrooms
    • Prep for wall tile installation
  • New Athletic Corridor/Elevator
    • Hydronic and electrical piping installation
    • Continued painting
    • Elevator installation

Planned week ending Friday, October 16, 2020

  • Boiler Room
    • Electrical and mechanical piping connections
  • Area P Link
    • Continue flooring
  • Lower Level Area F Dance Studio and Weight Room
    • Start weight room flooring
  • Area C 3rd level science rooms
    • Finish setting cabinets and tops
    • Start chemical resistant flooring
  • Area C 3rd level restrooms
    • Start wall and floor tiling
  • New Athletic Corridor/Elevator
    • Continue elevator installation
    • Continue mechanical and electrical rough ins

Centennial Elementary

Completed week ending Friday, October 9, 2020

  • Contractors worked to complete punch list items.
  • Contractors corrected issues noted on the IEA Commissioning corrective action log.
  • Continued working on boiler room piping.
  • Completed the installation of the new interior room signage.
  • All-State continued installing security system components.
  • ICS solicited proposals for new window treatments.

Planned week ending Friday, October 16, 2020

  • Contractor to continue working to address punch list items.
  • Contractor to continue working through testing and balancing of the mechanical/HVAC equipment.
  • Complete boiler system piping. Boiler start-up scheduled for 10/14.
  • All-State to complete the installation of all security system components.
  • Issue PO for new window treatments.

Sheridan Hills Elementary

Completed week ending Friday, October 9, 2020

  • Continued working to address punch list items.
  • Deficiencies checklist issued by the Testing and Balance contractor.
  • Continue Phase 2 mechanical piping in the Lower Level.
  • Completed the Kitchen/Receiving addition excavation and concrete footings, CMU foundation walls are in progress.
  • Xcel completed the relocation of the main electrical feed into the building in preparation for the Chiller Enclosure construction.

Planned week ending Friday, October 16, 2020

  • Contractors to continue working to address punch list items.
  • Contractors to work to address deficiencies noted on the Testing and Balancing deficiencies checklist.
  • Continue Phase 2 mechanical piping in the Lower Level.
  • All State to complete the installation of all security system components
  • Complete excavation at Receiving area addition.
  • Complete Kitchen/Receiving addition CMU foundation walls and backfill.
  • Begin excavation for the Chiller Enclosure addition.

Richfield Middle School

Completed week ending Friday, October 9, 2020

  • Phase 2 Area D Special Education/Link
    • Classroom painting
    • Continued plumbing rough ins in restrooms
  • Phase 2 New Conference Room and Staff Lounge
    • Wall prep for paint
  • Phase 2 FACS Lab
    • Started wall framing
    • Mechanical and electrical rough ins
  • Phase 2 Chiller Tower
    • Demolition of existing chiller enclosure
    • Dig and pour for underground footings
    • Excavate and start underground utilities
  • Phase 3 Third Floor Restrooms
    • Mechanical and electrical rough ins to continue

Planned week ending Friday, October 16, 2020

  • Phase 2 Area D Special Education/Link
    • Continue plumbing rough ins in restrooms
  • Phase 2 New Conference Room and Staff Lounge
    • Wall painting
    • Ceiling grid installation to begin
  • Phase 2 FACS Lab
    • Mechanical and electrical rough ins
  • Phase 2 Chiller Tower
    • Form and pour electrical transformer pad
    • Continue underground utilities
    • Start above grade masonry walls
  • Phase 3 Third Floor Restrooms
    • Mechanical and electrical rough ins to continue
    • Start wall framing

Richfield STEM Elementary

Completed week ending Friday, October 9, 2020

  • Testing, balancing, and commissioning of mechanical systems
  • Filled mechanical system with glycol
  • Started up boilers

Planned week ending Friday, October 16, 2020

  • Testing, balancing, and commissioning of mechanical systems

Richfield Dual Language School

Completed week ending Friday, October 9, 2020

  • Contractors continued working to address items noted on the commissioning corrective action log.
  • Contractors worked to address issues identified during the 11-month warranty walkthrough.

Planned week ending Friday, October 16, 2020

  • Contractors to continue working to address items noted on the commissioning corrective action log.
  • Contractors to continue working to address issues identified during the 11-month warranty walkthrough.