ICS Monthly Report: December 3, 2021

ICS Monthly Report: December 3, 2021

Each week, we will share the latest construction updates provided by ICS. If you would like to view past updates or learn more about our capital facilities plan, please visit the Facilities page. 


*This report is submitted from ICS on a weekly basis.

Maintenance/Transportation Building

Completed month of November 2021

  • 75% Construction Documents revised and completed.
  • 95% cost estimate completed.
  • Project approved by the school board for issuance to bid.
  • Project issued for bid.

Planned for month of December 2021 

  • Hold pre-bid walkthrough meeting.
  • Receive and tabulate bids.
  • Present recommendation to award contract to school board for approval.

Sheridan Hills Elementary

Completed month of November 2021

  • Completed site sodding.
  • Completed the installation of the coiling doors at the Kitchen/Cafeteria.
  • Exterior signage was installed.
  • Continued addressing punch list and commissioning items.
  • Continued to address open City and Health Dept. inspection items.

Planned for month of December 2021

  • Complete all open City and Health Dept. inspection items.
  • Contractors to continue addressing punch list and commissioning items.
  • Compile and review of Operation and Maintenance Manuals and attic stock.

Richfield Middle School

Completed month of October 2021

  • Continued punch list, commissioning, testing, and balancing
  • Dishwasher door and counter modifications

Planned for month of December 2021

  • Install exterior signage.
  • Best Buy Teen Tech Center room modifications (painting) to be completed.
  • Continue punch list, commissioning, testing, and balancing
  • Order furniture for Best Buy Teen Tech Center

Central Education Center

Completed month of November 2021

  • Sod installation completed.
  • All piping insulation, rooftop ductwork and boiler stacks completed.
  • Testing, Adjusting and Balancing of HVAC system.
  • BAS owner training.
  • Exterior façade repair.
  • Substantial completion of HVAC system.
  • Final building inspection and all permits closed.
  • Exterior signage installed.

Planned for month of December 2021

  • Install operable walls.
  • Deliver remaining backordered furniture.
  • ICS commissioning of boilers and hydronic systems.
  • Complete interior plaster repair in multipurpose room.
  • Compile and review of Operation and Maintenance Manuals and attic stock.
  • Complete remaining punch list items.

Download the PDF Report

Read More